Widening Bridge Reconstruction

Start Date: Spring 2008
Completion Date: Fall 2009
Total Cost: $19.2 million

Map of Macedonia and Northfield Center area.Project Description: Widening of SR 82 to five lanes from South Bedford Road to just east of Crow Drive with the replacement of a railroad bridge and a culvert over Indian Creek. The project also includes drainage improvements, traffic controls and signal improvements.

Maintenance of Traffic: Reconstruction of SR 82 will be done with part-width construction; however, there will be short term, temporary, nightime closures of SR 82 for the placement of bridge beams for the new railroad bridge. The SR 82 side streets of Valley View Road, North Bedford Road, Park Avenue, and Crow Drive will be closed for a period of time during the project. Detours will be provided. Access to all establishments and residences will be maintained during the project.